Winners never give up
World class performance requires speed, quality, agility and endurance
  
RCG Success Stories

World Class Manufacturing: Evaluating Capital Equipment for an Aerospace Manufacturer

Aerospace Manufacturer $50mm Sales Revenue

An aerospace pioneer had been a significant part of the world's aerospace community for more than seventy years, having designed and built many of the world's most famous and unusual aircraft. The company was an industry leader, not only producing high performance aerial target systems, unmanned aerial reconnaissance vehicles (UAV's) and the subcontract assembly of airframe structure, but also in the development and manufacture of ordnance products and small jet turbine engines.

The aircraft industry in the United States had changed dramatically. Two major manufacturers, Boeing and Northrop-Grumman, had significant backlog and insufficient capacity to meet their current orders.  This gave this company an opportunity to become a major fabricator and assembler of commercial airframes. 

In order to pursue this opportunity, the company needed to to restructure its manufacturing operation to improve profitability.  To accomplish that the company needed to upgrade and expand its manufacturing capacity with modern, advanced-technology equipment.  A capital budget was submitted for new equipment, but the request was put on-hold pending an independent assessment of the need for the equipment, and the benefits it would bring to the company.  Rockford Consulting Group. was retained to perform that independent assessment. The objectives of this effort were to:

  • Review the  manufacturing and fabrication equipment and assess the state of condition
  • Determine if the existing equipment should be upgraded, and if so, with what?
  • Estimate the effort and the benefits, and
  • Determine how to proceed
We began the effort with a detailed review of parts fabricated and machined and current manufacturing techniques.  Next, we spent a considerable amount of our time on the shop floor discussing machines, processes, set-ups, mixing, product mix, lot sizes, etc. We methodically reviewed and assessed equipment age, condition, and generation of technology for subcontract application.  We reviewed sales projections for firm contracts and orders most likely to materialize.  The sales projections represented a 64% increase from year 1 to year 2.  Using existing routings we converted the sales to machine hours. 

We reviewed the loads on the large 3X5 gantries and determined the load levels that could be off-loaded to smaller and less expensive machines.  We then assessed the existing equipment for capacity and determined what new equipment was required to meet capacity loading to meet year 2 sales projections.  New cycle times were established for parts manufactured with upgraded or new equipment.

When this was accomplished, we listed the type equipment required for year 1 and year 2 production volumes, and revised the year 1 proposed capital plan reflecting the changes. 

We reviewed the age, condition and technology of the equipment, and discovered a major cause of poor utilization.  The average age of the 39 pieces reviewed was 29 years.  Over 50 percent of the equipment were in excess of 30 years old.   Because most of the equipment was unable to perform multiple operations, set-ups were frequent.  This was compounded by low quantities of component parts being manufactured. 
 
World class performance requires speed, quality, agility and endurance

Older machines tended to breakdown more often due to excessive wear.  Downtimes were long because of machine breakdowns.  This also consumed plant capacity.  But since old machines tend to prevent substantial gains from occurring, rebuilding old equipment would not support a flexible and fast environment.  The old equipment was not capable of producing higher RPM's required for short cycle times.  The spindles simply would not turn fast enough. The effect of old equipment and equipment that was in poor condition can be seen in the chart below. 

World class performance requires speed, quality, agility and endurance

The utilization of equipment identified averaged 45%.  We discovered that machine capacities were imbalanced. But more significant was certain pieces of equipment were under capacity, limiting the ability of the current equipment to meet year 1 and year 2 shop loading requirements, and forced the operation to outsource the overload at a higher cost.  The limited capacity also prevented the manufacturing operation from meeting year 1 sales projections without outsourcing the overloaded hours.

World class performance requires speed, quality, agility and endurance

Of 39 machines evaluated, over 60 percent of the equipment were rated fair (5) to poor (1) condition.  Two machines were rated as (0) and needed to be scrapped.  One was a 1963 G&L 5-axis profile mill, that had 4 percent load hours and was being off-loaded to other equipment.  The second machine was a 16 year old Ekstrom Carlson Router.  This company no longer made these machines and parts were becoming unavailable.  We proposed to replace this machine in the capital plan with a (4) spindle 3 axis Shoda.

World class performance requires speed, quality, agility and endurance

The NC machines required major expenditures to completely retrofit.  Cost estimates for these 11 machines would have been approximate $4 million of which $1 million would have gone to retrofit a 5-axis profile mill.  This cost expenditure was questionable and further analysis indicated a new machine could be purchased for $600 K .  Our revised plan was to retrofit 7 of these machine for a cost of $2,450 K.  This equated to approximately $1.5 million savings.

World class performance requires speed, quality, agility and endurance

Most of the other pieces of equipment required maintenance to be performed in order to produce aerospace  piece parts to drawing specifications.  Major expenditures were required for the Knapp-Lee and Lindberg furnace for heat treat operations.  Another maintenance expense was for the Verson Europa Press to upgrade the bladder system design.

As we continued our evaluation, we discovered that total lead times were long.  For example, value-add time was low compared to the total time through the factory.  For a simple time and material order to pass through the factory from receipt to shipment, 28 days were typically consumed.  Yet 14-15 minutes of this time was actual consumed by spindles cutting metal from a component (value-add).  The remaining time parts were waiting for something to happen. The study revealed that the total of a fixed price contract extended from 26 to 54 weeks at the extreme.  This throughput time is indicative of a slow business process, presumably reflective of long lead times experienced in government contracting. 

This would not work for commercial markets.  Lead times in commercial markets were compressing quickly as companies devise ways to become more competitive.  For this company to be competitive in the commercial markets, total throughput times had to be less than 30 days.  This included time for quotations, order entry, engineering, procurement, scheduling and manufacture. 

Capacity requirements for year 1 increased over year 2 by 64%.  Upgrades to some equipment, plus additional pieces of equipment were required to make the parts to meet sales projections. As a result of our review we recommended the following:

1. Repair, upgrade and replace some of the existing equipment.

2. Add additional equipment to increase current capacity to meet year 2 sales projections

3. Reduce the proposed year 1 capital plan by $8,882,880

When smaller parts that were slated to be run on the large 3X5 gantries were off-loaded to smaller machines, the need for additional gantries in the near-term were negated.  The resultant cost of capital was $8.8 mm less than the original plan.  The capital plan represented the acquisition of eight new CNC machines, a new CMM, additional NC programming computers, retrofitting seven existing CNC machines, and replacing one manual machine with a used machine within the year 1 and year 2 calendar year. (Please see our World Class Manufacturing consulting services World Class Manufacturing Consulting Services )


| To go to Home Page, click here |

|Site Map|