![]() ![]() |
|
RCG Success Stories
World Class Manufacturing: Evaluating Capital Equipment for an Aerospace Manufacturer Aerospace Manufacturer $50mm Sales Revenue An aerospace pioneer had been a significant part of the world's aerospace community for more than seventy years, having designed and built many of the world's most famous and unusual aircraft. The company was an industry leader, not only producing high performance aerial target systems, unmanned aerial reconnaissance vehicles (UAV's) and the subcontract assembly of airframe structure, but also in the development and manufacture of ordnance products and small jet turbine engines. The
aircraft industry in the United States had changed dramatically. Two
major manufacturers, Boeing and Northrop-Grumman, had significant
backlog and insufficient capacity to meet their current orders.
This gave this company an opportunity to become a major fabricator and
assembler of commercial airframes.
We
began the effort with a detailed review of parts fabricated and
machined and current manufacturing techniques. Next, we spent a
considerable amount of our time on the shop floor discussing machines,
processes, set-ups, mixing, product mix, lot sizes, etc. We
methodically reviewed and assessed equipment age, condition, and
generation of technology for subcontract application. We reviewed
sales projections for firm contracts and orders most likely to
materialize. The sales projections represented a 64% increase
from year 1 to year 2. Using existing routings we converted the
sales to machine hours.
We
reviewed the loads on the large 3X5 gantries and determined the load
levels that could be off-loaded to smaller and less expensive
machines. We then assessed the existing equipment for capacity
and determined what new equipment was required to meet capacity loading
to meet year 2 sales projections. New cycle times were
established for parts manufactured with upgraded or new equipment.
When
this was accomplished, we listed the type equipment required for year 1
and year 2 production volumes, and revised the year 1 proposed capital
plan reflecting the changes. We
reviewed the age, condition and technology of the equipment, and
discovered a major cause of poor utilization. The average age of
the 39 pieces reviewed was 29 years. Over 50 percent of the
equipment were in excess of 30 years old. Because most of
the equipment was unable to perform multiple operations, set-ups were
frequent. This was compounded by low quantities of component
parts being manufactured. ![]() The
utilization of equipment identified averaged 45%. We discovered
that machine capacities were imbalanced. But more significant was
certain pieces of equipment were under capacity, limiting the ability
of the current equipment to meet year 1 and year 2 shop loading
requirements, and forced the operation to outsource the overload at a
higher cost. The limited capacity also prevented the
manufacturing operation from meeting year 1 sales projections without
outsourcing the overloaded hours. ![]() Of 39 machines evaluated, over 60 percent of the equipment were rated fair (5) to poor (1) condition. Two machines were rated as (0) and needed to be scrapped. One was a 1963 G&L 5-axis profile mill, that had 4 percent load hours and was being off-loaded to other equipment. The second machine was a 16 year old Ekstrom Carlson Router. This company no longer made these machines and parts were becoming unavailable. We proposed to replace this machine in the capital plan with a (4) spindle 3 axis Shoda. ![]() The
NC machines required major expenditures to completely retrofit.
Cost estimates for these 11 machines would have been approximate $4
million of which $1 million would have gone to retrofit a 5-axis
profile mill. This cost expenditure was questionable and further
analysis indicated a new machine could be purchased for $600 K .
Our revised plan was to retrofit 7 of these machine for a cost of
$2,450 K. This equated to approximately $1.5 million
savings. As we continued our evaluation, we discovered that total lead times were long. For example, value-add time
was low compared to the total time through the factory. For a simple
time and material order to pass through the factory from receipt to
shipment, 28 days were typically consumed. Yet 14-15 minutes of this
time was actual consumed by spindles cutting metal from a component (value-add).
The remaining time parts were waiting for something to happen.
The study revealed that the total of a fixed price contract extended
from 26 to 54 weeks at the extreme. This throughput time is
indicative of a slow business process, presumably reflective of long
lead times experienced in government contracting. This
would not work for commercial markets. Lead times in commercial
markets were compressing quickly as companies devise ways to become
more competitive. For this company to be competitive in the
commercial markets, total throughput times had to be less than 30
days. This included time for quotations, order entry,
engineering, procurement, scheduling and manufacture. Capacity
requirements for year 1 increased over year 2 by 64%. Upgrades to
some equipment, plus additional pieces of equipment were required to
make the parts to meet sales projections. As a result of our review we
recommended the following: When smaller parts that were slated to be run on the large 3X5 gantries were off-loaded to smaller machines, the need for additional gantries in the near-term were negated. The resultant cost of capital was $8.8 mm less than the original plan. The capital plan represented the acquisition of eight new CNC machines, a new CMM, additional NC programming computers, retrofitting seven existing CNC machines, and replacing one manual machine with a used machine within the year 1 and year 2 calendar year. (Please see our World Class Manufacturing consulting services World Class Manufacturing Consulting Services ) |